Solid Fuel Central Energy Plant Installation

Industrial Boiler provided and installed this complete central energy plant which consisted of two field assembled Combustion Engineering Power Boilers, one Babcock & Wilcock 50,000 lb.hr package back up boiler, 90,000 lb/hr D.A. system, condensate surge/storage system, Zurn dust collectors and all solid fuel controls and handling system.

This plant was designed and built to provide steam to two separate manufacturing facilities. This 2nd phase of the project required IB&M to provide engineering and field services to build this massive pipe highline and provide over 2 ½ miles of piping which included steam, condensate, natural gas, compressed air, city water piping and saw dust return duct from both plants to/from the Central Energy Plant.